Establish the evidence

At contract day 355, weighted actual progress stood at 16% against 48% planned.

Verified project snapshot

Evidence basis

One real snapshot. No fabricated data.

Every number in this lab comes from verified information for Ozgol Residential Towers. The visuals do not imply an invented time series.

Planned progress48%
Actual progress16%
32Gap355Contract day joined470Accepted delay days